Kran supported a complex lifting and positioning operation at a port facility in Constanța. Our team installed a large industrial weighing structure onto an elevated steel support.
Due to the structural configuration and load sensitivity, we deployed two mobile cranes working in tandem. One crane performed the primary lift, while the second stabilized the load to prevent torsional stress on the supporting elements during positioning.
The lift was executed with precision, controlled movements, and continuous monitoring, ensuring safe installation at height within a limited operational window.
Equipment Used
- Mobile crane – Terex Demag AC100-5 (100 t capacity)
- Auxiliary mobile crane for load stabilization
- Certified lifting accessories and rigging equipment
Technical Details
- Load weight: approx. 11 t
- Load geometry: rectangular / parallelepiped (approx. 2.5 m × 2.5 m)
- Installation height: support at approx. 10 m
- Maximum lifting height: approx. 25 m
- Duration: approx. half-day operation
- Working environment: port / industrial area
Scope of Work
- Site assessment and lift planning
- Tandem crane configuration
- Controlled lifting and load stabilization
- Precision positioning at height
- Safe demobilization after completion