Kran provided professional access-at-height support for inspection and maintenance works carried out beneath the A2 Motorway viaduct at km 198+200, in the Murfatlar area.
The operation was performed using an articulated aerial work platform mounted on a Nissan Cabstar F24 (Tecchio M22 LEON), with an approximate working height of 21 meters.
The works included providing safe vertical access to the underside of the viaduct structure, enabling technical activities to be carried out in controlled and stable conditions.
Given the limited space, the intervention required precise positioning, full stabilization with outrigger pads/cribbing, and continuous on-site coordination.
All operations were carried out by authorized operators, in accordance with approved safety procedures, ensuring continuity and efficiency throughout the intervention.
Technical details
- Location: A2 Motorway Viaduct, km 198+200 (Murfatlar area)
- Equipment: Nissan Cabstar F24 – Tecchio M22 LEON
- Equipment type: articulated boom aerial work platform
- Working height: approx. 21 m
- Scope of work: access for inspections and maintenance
- Work environment: road infrastructure
- Duration: multi-day operation
- Intervention type: access-at-height with operator and full stabilization