Description:
Kran provided heavy-equipment support for the transport and assembly of a complete concrete batching plant in Mihail Kogălniceanu (Constanța County). The project required multiple cranes and access platforms over several days of coordinated lifting.
Equipment Used:
- 45t mobile crane
- 100t mobile crane
- 21m rubber-wheeled aerial work platform
Location:
Mihail Kogălniceanu, Constanța County
Duration:
July – August 2025
Scope of Work:
- Lifting and positioning concrete silos
- Assembly of mixing units and structural frames
- On-site support with aerial platforms for safe assembly at height
Technical Notes:
- Truck-mounted cranes with safe lifting capacities up to 100t
- Deployment included ground stabilization with outriggers
- Precise rigging and coordinated lifts for tall vertical structures