Kran deployed a 100-ton mobile crane (Terex Demag AC100-5) to support high-reach industrial maintenance works at CET Palas, B-dul Aurel Vlaicu nr. 123, Constanța, with access via Strada Industrială.
The project required lifting operations at a significant height, with loads positioned at approximately 52 meters on the upper sections of a large cylindrical structure surrounded by full scaffolding. Our team executed all lifts safely, ensuring stable crane positioning, precise boom extension, and continuous coordination with the on-site contractor.
Scope of Work
- Positioning the 100T crane in a constrained industrial area
- Full outrigger deployment and ground stabilization checks
- High-reach lifting operations (approx. 3 t at 52 m)
- Controlled handling of steel and maintenance components
- Coordination with ENERGOMONTAJ SA specialists
- Completion of the project within a single operational day
Equipment Used
- Terex Demag AC100-5 – 100-ton mobile crane
- Hydraulic telescopic boom
- Certified rigging accessories
- On-site certified operator + signaler
Location
CET Palas, B-dul Aurel Vlaicu 123 – Constanta (Access via Str. Industrială)
Duration
1 day of crane operation
Technical Details
- Maximum working height: 52 m
- Load handled: approx. 3 t
- Outriggers fully extended
- Industrial confined-space setup
- Operation supported under monitored site conditions