Kran provided a truck-mounted crane (Scania R164G 8x4 FASSI F900XP – 20 t) to support lifting operations on an ongoing residential construction project located on Str. Eduard Caudella, Constanța.
The job required the precise handling and placement of heavy construction materials—including reinforcement steel bundles and timber elements—up to the second floor (approx. 12 m height) with a working radius of 7 m.
The operator set the crane in place, deployed the outriggers, and oversaw the lifts.
Scope of Work
- Positioning the crane on a narrow urban roadway
- Lifting approx. 10 tons of reinforcement steel
- Vertical lifting to ~12 m height (Floor 2)
- Controlled placement of timber and steel on upper levels
- Coordination with site workers for safe material handling
- Multiple lifts completed within the scheduled work window
Equipment Used
- Scania R164G 8x4 – FASSI F900XP (20 t) Truck-Mounted Crane
- Certified lifting chains and slings
- Full hydraulic stabilization system
Location
Strada Eduard Caudella 13B, Constanța, Romania
Duration
Single-day operation (Multi-hour lifting support)