The work took place in the Lazu area of Agigea and involved loading a 20-ton container onto a transport platform. The request required a fast intervention, with limited working space next to the logistics building.
A mobile crane was used for the main lift, while a truck-mounted crane supported the positioning and handling operations. The container was rigged with lifting slings and raised in a controlled sequence to the platform level.
The operation was completed in less than a day. The main steps were preparing the work area, rigging the container, lifting the load and placing it onto the trailer for transport.