Description:
Kran provided two mobile cranes to support TransTruck VLD for a half-day heavy lifting operation at Port Constanța, Dana 89–90 (Steel Cems yard). The job involved the coordinated unloading of excavator components and a tubing machine weighing approximately 60 tonnes from a truck, followed by positioning and mounting of the excavator.
Equipment Used:
Location:
Port Constanța – Dana 89–90, in the yard of Steel Cems SRL
Duration:
Half day
Scope of Work:
Technical Notes
Lifting Configuration:
Rigging: Dual-crane tandem lift with spreader bars and heavy-duty chain slings
Ground Conditions: Compacted yard surface with wet patches; steel mats used for stability where necessary
Safety Measures:
Special Considerations: